[TYO] Hardware Maintenance
Scheduled Maintenance Report for tyo
Completed
CloudSigma would like to inform you that the scheduled Hardware maintenance on our infrastructure in the Tokyo cloud location has been performed successfully. During the maintenance, we replaced failed drive in one of the storage nodes, sustaining the storage cluster.

IMPACT:
There was no impact on any of the existing servers, drives, or networking, as the equipment has the required level of redundancy.
Posted Jan 04, 2024 - 12:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 04, 2024 - 11:00 UTC
Scheduled
CloudSigma would like to inform you that we are planning to do scheduled maintenance in the Tokyo cloud location. We will be replacing a failed drive in one of the storage nodes, part of the storage cluster. The actual works are planned to take no longer than 9 hours in total.

IMPACT:
There will be no impact on already existing/running customers’ virtual machines, hosts, network accessibility, and/or any other running services.
Posted Dec 28, 2023 - 05:42 UTC
This scheduled maintenance affected: Tokyo Cloud.